Keep one row per approval, with the reviewing office, current source, required drawing, fee basis, prerequisite, responsible person and status. Mark a verbal preliminary discussion differently from an issued permit. Record the approved drawing revision so suppliers and trades build from the same information.
- Land use: dwelling, accessory structures and any business activity
- Site: survey, access, drainage, floodplain and easements
- Wastewater and water: feasibility, design and authority approval
- Building: structure, foundation, energy and trade permits
- Completion: required inspections and occupancy documentation